Fives sets a new record for the manufacture of a cold box
In only 3 months, the Energy | Cryogenics teams built a cold box for a gas plant in Saudi Arabia for Hyundai Engineering & Construction Co., Ltd, an impressive record time!
Indeed, it usually takes 6 to 8 months to design and manufacture similar cold boxes.
Weighing 52 tons and composed of 3 brazed aluminum heat exchangers (BAHX), the cold box could be built thanks to the skills, energy, and involvement of the teams, who had to, on top of a tight schedule, also work while complying with safety protocols in a time of Covid-19 and distancing rules.
Fives is proud of its Energy | Cryogenics teams’ great achievement as well as their commitment to go the extra mile to answer their client's needs.