Here is the preview url to copy
+

https://www.fivesgroup.com/cn/%E7%89%B9%E6%AE%8A%E9%A1%B5%E9%9D%A2/%E9%A2%84%E8%A7%88
Skip to main content

First slab from the highest capacity reheating furnace

Fives and JSW Dolvi Works, part of India’s leading steel producer JSW Steel, successfully discharged the first hot slab from the reheating furnace on March 31, 2021.


JSW Steel contracted Fives to design and supply two reheating furnaces - Stein Digit@l Furnace® - for their new hot strip mill at Dolvi works in the state of Maharashtra. The furnaces have the highest capacity installed in India to date - each 450 tonnes per hour - and feature high environmental performance and low fuel consumption. 

The first furnace was ignited in January 2021. “It required a lot of dedication and continuous efforts from our team to work on site during the challenging period, but we were very determined,” says Chandrajit Sinha, Project Manager at Fives Stein India Projects, a Fives’ subsidiary in India.

“Our strength was our local manufacturing capabilities and the dedication of our team to work through these difficult times. We achieved more than 85% localization and discharged the first slab in very good conditions without skewness or skid marks,” commented Asis Das, Head of Project Management at Fives Stein India Projects

“We appreciate Fives’ team determination to commission the first furnace in the extreme conditions due to the national lockdown. It’s an important milestone in our cooperation by definition,” says Ashutosh Sharma, Project Head - Hot Strip Mill at JSW Steel
 

 

高附加值的工业解决方案

 

法孚为全球各大工业企业设计和制造机械、工艺设备以及生产线。

集团集团在整个价值链中,为其客户提供全周期的技术支持。
法孚不断突破工业工程的界限,致力于提供更贴近客户需求的解决方案。

 

  50秒集团掠影法孚概览

 

作为工业领军者这家法国的全球化机构
稳步发展并迅速崛起
 

 

​​​​​法孚招聘  我们的分布

 

法孚,未来工业的领军企业

法孚在技术及服务中融入了数字化、预测性维护、金属3D打印、机器人技术、能源优化等解决方案。致力于设计和打造当下与未来的互联工厂。  

 

创新     人工智能和数据处理    增材制造    环境保护

新闻与报道

First slab from the highest capacity reheating furnace

Fives and JSW Dolvi Works, part of India’s leading steel producer JSW Steel, successfully discharged the first hot slab from the reheating furnace on March 31, 2021.


JSW Steel contracted Fives to design and supply two reheating furnaces - Stein Digit@l Furnace® - for their new hot strip mill at Dolvi works in the state of Maharashtra. The furnaces have the highest capacity installed in India to date - each 450 tonnes per hour - and feature high environmental performance and low fuel consumption. 

The first furnace was ignited in January 2021. “It required a lot of dedication and continuous efforts from our team to work on site during the challenging period, but we were very determined,” says Chandrajit Sinha, Project Manager at Fives Stein India Projects, a Fives’ subsidiary in India.

“Our strength was our local manufacturing capabilities and the dedication of our team to work through these difficult times. We achieved more than 85% localization and discharged the first slab in very good conditions without skewness or skid marks,” commented Asis Das, Head of Project Management at Fives Stein India Projects

“We appreciate Fives’ team determination to commission the first furnace in the extreme conditions due to the national lockdown. It’s an important milestone in our cooperation by definition,” says Ashutosh Sharma, Project Head - Hot Strip Mill at JSW Steel
 

First slab from the highest capacity reheating furnace

Fives and JSW Dolvi Works, part of India’s leading steel producer JSW Steel, successfully discharged the first hot slab from the reheating furnace on March 31, 2021.


JSW Steel contracted Fives to design and supply two reheating furnaces - Stein Digit@l Furnace® - for their new hot strip mill at Dolvi works in the state of Maharashtra. The furnaces have the highest capacity installed in India to date - each 450 tonnes per hour - and feature high environmental performance and low fuel consumption. 

The first furnace was ignited in January 2021. “It required a lot of dedication and continuous efforts from our team to work on site during the challenging period, but we were very determined,” says Chandrajit Sinha, Project Manager at Fives Stein India Projects, a Fives’ subsidiary in India.

“Our strength was our local manufacturing capabilities and the dedication of our team to work through these difficult times. We achieved more than 85% localization and discharged the first slab in very good conditions without skewness or skid marks,” commented Asis Das, Head of Project Management at Fives Stein India Projects

“We appreciate Fives’ team determination to commission the first furnace in the extreme conditions due to the national lockdown. It’s an important milestone in our cooperation by definition,” says Ashutosh Sharma, Project Head - Hot Strip Mill at JSW Steel
 

First slab from the highest capacity reheating furnace

Fives and JSW Dolvi Works, part of India’s leading steel producer JSW Steel, successfully discharged the first hot slab from the reheating furnace on March 31, 2021.


JSW Steel contracted Fives to design and supply two reheating furnaces - Stein Digit@l Furnace® - for their new hot strip mill at Dolvi works in the state of Maharashtra. The furnaces have the highest capacity installed in India to date - each 450 tonnes per hour - and feature high environmental performance and low fuel consumption. 

The first furnace was ignited in January 2021. “It required a lot of dedication and continuous efforts from our team to work on site during the challenging period, but we were very determined,” says Chandrajit Sinha, Project Manager at Fives Stein India Projects, a Fives’ subsidiary in India.

“Our strength was our local manufacturing capabilities and the dedication of our team to work through these difficult times. We achieved more than 85% localization and discharged the first slab in very good conditions without skewness or skid marks,” commented Asis Das, Head of Project Management at Fives Stein India Projects

“We appreciate Fives’ team determination to commission the first furnace in the extreme conditions due to the national lockdown. It’s an important milestone in our cooperation by definition,” says Ashutosh Sharma, Project Head - Hot Strip Mill at JSW Steel