 11/4/2010 

 Unit shutdown of the Michelin plant completed successfully  

 

 

Fives Nordon carried out maintenance and inspection work at the Michelin plant in Bassens. This order involved 139 different workstations and required 50 people (including 15 supervisors) and 50 subcontractors.

Their professionalism, availability and adaptability enabled to achieve work within five days. To meet this very tight deadline, Fives Nordon, which was responsible for preparing the shutdown, drew up an hourly schedule for each task.

The project was carried out successfully and in fully safe conditions since no accident nor first aid were deplored, thanks to the vigilance of the whole team, and the permanent support of a site safety coordinator. Recommissioning of the plant was also carried out successfully, with no leaks recorded.

News

03/19/2014: Fives Group will attend the 34th Forum Arts & Métiers ParisTech 2014

In March 27th 2014, the Fives Group will attend...

 >> Read more | More news

02/17/2014: Fives Stein key contract with Indian steel maker JSPL for a reheating furnace

  Fives Stein, a leading designer and supplier...

 >> Read more | More news

01/03/2014: Fives delivers an HAPL to Chinese Steelmaker SWSS

Paris, January 3, 2014 – Fives has just signed...

 >> Read more | More news

Careers

Managing skills based on respect for employees

Fives implements a human resources policy that...

 >> Our offers | Read more

Corporate Social Responsibility

As an industrial engineering group, Fives is at...

 >> Read more


Fives Back to home

Fives © 2009